how to install the Formwork Concrete Placing Boom-Industry News-Truemax makes concrete equipment manufacturing and direct sales-

>> Events & News >> Industry News

how to install the Formwork Concrete Placing Boom

  The Formwork Concrete Placing Boom is an intelligent placing machine that cooperates with the formwork climbing.It can be synchronized with the formwork climbing system when in use,reducing the operation of secondary climbing.It is also a relatively recognized method for many high-rise building projects.


  The installation of the Formwork Concrete Placing Boom is very convenient,and the safety has also been recognized by many projects.The installation methods are as follows:


how to install the Formwork Concrete Placing Boom

  1.The first is to choose the installation position of the Formwork Concrete Placing Boom.It is generally installed at the center point of the floor.The 360-degree rotation of the placing machine can achieve all-round pouring.The tower crane hoists the base of the formwork placing machine to the installation position for full welding and hooping or locking the legs and the formwork connection with a splint.point,play the role of double protection.


  2.Carry out the structural installation on the formwork placing machine.Tops are divided into:swivel seat,guardrail,cloth boom.They can be installed separately or as a whole,depending on the hoisting weight range of the tower crane.If the hoisting weight requirements cannot be met,they must be disassembled and hoisted,and then assembled.

Mold frame distributor installation

  3.After the placing machine is installed,a wireless remote control test should be carried out on site to check whether there is any abnormality in the Formwork Concrete Placing Boom.The after-sales engineer needs to train the operators to learn the knowledge of maintenance and abnormal situation solutions.